How To Create Baseline In Ms Project
How to update Baseline and Save actual data in MS PROJECT 2013?
Hi,
I have a question from my Blog reader: "Hi, How can I update Baseline with new Tasks if Project has Tasks with Actual data, e.g I don't want to loose those actual data, nor I want to change Baseline for those Tasks"
It is very simple. I will show how to do that in MS PROJECT 2013.
First I am going to Create new Project with three Tasks, and I will link them:
Now I am going to save the Baseline:
and then:
OK, let's look at the Tracking Gantt View:
Now suppose that Task 1 was started at 26.02.2014, and finished at 01.10.2014:
and then:
and I'll get:
Now suppose that I have another two Tasks:
Those Task are not "Baselined" as you can se at the Picture above. Now, if I save the Baseline as I did for the whole Project I will get:
As you can see, Baseline is aligned with Actual data for Task1 to Task 3, and I do not want that.
So I will Select only new Task and I will create Baseline like this:
and I will get:
As you can see, Task 4, and Task 5, are now "Baselined", and Task 1, Task 2, and Task 3, are as they was!
Hope this helps!
Regards!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management and tagged Microsoft Project 2010, Microsoft Project 2013, Microsoft Project 2013-Baseline, MS PROJECT, MS PROJECT 2010, MS PROJECT 2013. Bookmark the permalink.
How To Create Baseline In Ms Project
Source: https://ntrajkovski.com/2014/09/24/how-to-update-baseline-and-save-actual-data-in-ms-project-2013/
Posted by: tanneronsch1951.blogspot.com
0 Response to "How To Create Baseline In Ms Project"
Post a Comment